Pavement reconstruction in the Homewood Hills Neighborhood is scheduled to begin as early as Monday, May 18th. Segments to begin in order with estimated start dates are as follows:

  • Viking Road - 1726 Viking Road to Miles Drive: May 18th
  • Oakwood/Briarwood Drive - near Miles Dr to 1330 Briarwood Drive: May 21st
  • Maplewood Drive - 1080 Maplewood Drive to Pinewood Drive (curve): May 27th
  • Pinewood Drive - Maplewood Drive (curve) to Miles Drive: June 1st

Work for each segment will take approximately three weeks, including at least seven days for the concrete to harden after it is placed. Weather conditions may extend the length of time required to return the street segment to use.

Drive carefully near the construction zones. Please reduce your speed and watch for construction equipment. There will be future News Releases as the pavement work progresses in the neighborhood.

All work will be completed by mid August 2020.